Coopers Stadium Upgrade
$1M
Hansen Yuncken
2024
Targeted demolition and removal works safely delivered under approved risk and stadium operational protocols.
Staged demolition within a live sporting environment
Project Scope:
Part of the Coopers Stadium redevelopment in Adelaide, this project involved a staged demolition package to prepare the Western Stand for major upgrade works:
- Stage 1 demolition as per approved drawings and addenda, including turnstile plinth removal
- Removal and disposal of approximately 40 m² of Level 4 Western Stand corridor ceiling
- Execution of 10 exploratory concrete slab cut-outs, each approximately 500 mm × 500 mm, including cutting, removal and disposal
- Waste management and controlled material removal